After waiting all week for the frames, we were told yesterday that the framing company are suggesting that we do treated pine frames due to the area possibly having termites!!!!
We had this discussion with the builder in the beginning and it was him that said he used some other way to stop termite damage and trusted that was all that was needed
Well $6500 later and a few choice words thrown around, we payed it and now the frames will take another 3 days to build..grrrrrr
So that leaves us with:
Friday - Plumbing should be done
Monday - frames delivered
Tuesday - frames stood
Wednesday - frames finished
And so we wait...