Saturday 5 May 2018

1 week to go ...

Whilst we're counting down the days, the guys doing the driveway started nice and early this morning and were up at the house getting ready before we arrived at 7am

There trucks everywhere in the street so lucky we only have 2 neighbours that are already in who didn't mind the noise

They started down the back shed first around 9:30am or so and then headed up the front to do the main one around midday or so

We just thought they'd just prep it all and go home...how wrong were we!

They stayed up until 7ish or so and when loading the machinery onto the trucks, they had to have the spotlights on to see, what a big day!


I can't wait until we get the landscaping done and to have all the grass grow back and finally rid of all the rubbish that's left lying around...typical construction site as you would expect lol

The chippies came to finish off with the install of the door handles and pretty much stayed all day too. The only thing they have to finish is the rails in the wardrobes and towel rails in the bathrooms as well as the toot roll holders

The cleaners will start on Monday and Tuesday, the painters will be back to do the skirting and any touch ups as well as painting the rest of the mouldings

The gas heater will be installed either Monday or Tuesday as well and Ben (sparky) will finish off the rest of the electrical work

I think the new balcony door will be installed on Tuesday as well as the hand rail.
Thursday, the appliances  will be fitted...yay, can't wait to see how they look, and then it's handover day on Friday...yippee!